My Expected Submittals Log

This page lists the submittal actions which you are expecting or are expected from you in the current Project Center project.

Submittals categories

Use the Submittals drop-down list to filter the list of submittals by category. The categories are as follows:

Expected

This category lists all submittals logged as expected to which you are assigned.

Expected Resubmission

This category lists expected submittals assigned to you that were created for submittals that require the sender to resubmit the submittal (the action taken on the submittal was Rejected or Revise and Resubmit).

Late

This category lists expected submittals assigned to you that are overdue.

 

Columns

Overdue

The icon displays to the left of submittals that are overdue. The    icon displays to the left of submittals that are due in 8 days or less.

ID

The ID number of the submittals.

Sender ID

The number the contractor gave to the submittals.

Subject

The subject of the submittal. Select to open the Submittal page.

Expected Date

The date the submittal is expected from you.

Type

The submittal type.

Tasks

The Tasks drop-down list displays available tasks that can be performed for the submittal. Select a task from the list as needed.

 

Log Page Tools

The following tools are available in the My Expected Submittals log toolbar. For more information, refer to Log Page Tools.

Send Submittal

Click to open the Send Submittal page to add a new submittal.

 

To access this page

From the toolbar, select View > Contract Management > Submittals, then select the My Expected Submittals tab.

If submittals are not available to you, see Make a Project Center Project and Its Activity Centers Available on Info Exchange.