Re-Open Construction Change Directive dialog box
Re-Open Construction Change Directive dialog box
Use this dialog box to re-open a closed construction change directive.
Re-Opened By
Click to open the Choose a Project Team Member dialog box to choose the project team member who re-opened the construction change directive.
Reason
Select the reason for re-opening the construction change directive.
Remarks tab/Email Log tab/Related Items tab/Change Log tab
Refer to the Forward Construction Change Directive for Review dialog box for a description of these tabs.
Keywords
Click to open the Choose Keywords dialog box to apply keywordsIn Project Center, keywords are words you can add to items to use for filtering. When you add keywords, they appear in the Keywords column of the corresponding Project Center activity centers. You can then filter the list of items using the keywords to quickly find the items you are looking for. to the construction change directive.
Click to spell check the fields in this dialog box. If any mistakes are found, the Spelling dialog box opens with spelling suggestions.
To access this dialog box
You can access this dialog box in the following ways:
-
Select a closed construction change directive, then click Reopen from the Tasks panel of the Construction Change Directives activity center.
-
Expand a construction change directive’s list of actions, then select an action of type Reopened and click Modify Action from the Tasks panel.