Set Up Construction Change Directives

1 minute
10 months ago

Set Up Construction Change Directives

Perform the following steps to set up construction change directives on Info Exchange.

To set up construction change directives

The Construction Change Directives log must be configured to display on Info Exchange for the current project. To configure the project to display the log on Info Exchange, please see Make a Project Center Project and Its Activity Centers Available on Info Exchange.

You must be a member of the project team. To add a new member to the project team, please see Add New Project Team Members.

You must have access to the project on Info Exchange. To grant access to the project on Info Exchange to project team members, please see Add New Project Team Members.

You must be assigned to a permission set that grants access to view the Construction Change Directives log. For information on assigning a project team member to a permission set, please see Permission Sets.