Import Sketches and Supplemental Drawings from a Spreadsheet

6 minutes
12 months ago

Import Sketches and Supplemental Drawings from a Spreadsheet

This topic offers guidelines on creating a spreadsheet template in Microsoft Excel for importing existing sketches and supplemental drawings into Project Center.

You can access the sample sketches and supplemental drawings spreadsheet template supplied with Project Center in the following location: C:\Program Files\Newforma\Twelfth Edition\Project Center\Templates\Import_Sketches_Template.xlsx

You must be a Project Center administrator to perform this procedure.

Requirements overview

The following fields are common to all workflow-based contract management (CM) items:

Draft Status

If the item being imported does not have any workflow transmittals associated with it (no receive and no closing action), it must either be a draft or expected item. In these cases the following fields are required:

  • Draft Status – Must match a keyword in the workflow status list assigned to this item type in the Edit Project Settings dialog box. Only Workflow Expected or Workflow Draft keyword types are allowed for this field.

  • Expected Date – The date that this item is expected. This field must have a value if the Draft Status field was set to a keyword of type Workflow Expected.

Received Items

If the item being imported is to have a receive action created for it, the following fields are required:

  • Received Date – The date the item was received.

  • Received From – Who the item was received from.

  • Received By – Who received the item into the system.

  • Receive Action – The action for the received transmittal. This must match one of the actions defined in the keyword list that is assigned to this project for this CM item type in project settings.

  • Received Via – This much match one of the physical transfer methods in project settings, or Email or Info Exchange.

  • Receive Remarks – The remarks for the receive action.

Closed Items

If the item being imported is closed, it needs a closing action created for it. The following fields are required unless noted otherwise:

  • Closing Method – This field is required and describes what kind of closing the item had. CM items can be closed directly (Close), closed on a reply (Respond and Close), or on a send (Send and Close). The valid values for this field are closed, responded, or sent. This value will determine the type of closing transmittal action created.

  • Closed By – Who closed the item.

  • Closing Date – The date the item was closed.

  • Closing Action – The action for the closing transmittal. This must match an action defined in the keyword list that is assigned to this project for this CM item type in project settings. Note that there are different keyword list assignments for the various closing methods, so the list that this value is matched against depends on the value in the Closing Method field.

  • Closing Remarks – The remarks for the closing action.

  • Sent To – This field should only be set if the Closing Method field was set to sent. In this case it is required and should be the contact the item was sent to.

Sketches and supplemental drawing fields

The import spreadsheet has the following fields:

  • id – The ID of the sketch. This field is required if the project settings for sketches are set to manual numbering.

  • subject – (Required) The subject of the sketch.

  • type – (Required) The type of sketch. This must match a keyword in the sketch types keyword list assigned to sketches in project settings.

  • status – (Required) The status of the sketch. This must match a keyword in the sketch status keyword list assigned to sketches in project settings.

  • discipline – The disciplines that apply to the sketch. Separate multiple values with a semicolon. Whether all entries must already be in the discipline keyword list depends on the project settings for sketches.

  • reasons – The reasons for the sketch. Separate multiple values with a semicolon. Whether all entries must already be in the reasons keyword list depends on the project settings for sketches.

  • created by – Who created the sketch.

  • file – The file this sketch is tracking. This should be a full UNC path to the drawing in one of the project folders.

  • description – The description of the sketch.

  • internal notes – The internal notes for the sketch.

  • keywords – The keywords that apply to the sketch. Separate multiple values with a semicolon. Whether all entries must already be in the project keywords keyword list depends on the project settings for sketches.

  • email log – Existing email messages that should be included in the email log for this sketch. This field should contain full UNC paths to email files in the project folders. Separate multiple entries by a single asterisk (*).

  • supporting docs – Existing files that should be included in the supporting documents for this sketch. This field should contain full UNC paths to files in the project folders. Separate multiple entries by a single asterisk (*).

  • source descriptor – If items are being imported from another data source and will receive periodic one-way updates from that data source, then this field is a descriptor for that data source.

  • source primary key – If items are being imported from another data source, this is the unique identifier for this item in the external data source. This is used to ensure any updates received from the external data source are applied to the correct item in the Project Center database.

To create an import file for sketches and supplemental drawings and import it

Make a backup copy of your existing spreadsheet with the data.

Edit the spreadsheet and fill in the required data:

  • Remove any extra rows.

  • Determine how your fields map to Project Center fields (you can rearrange columns to match Project Center columns).

Copy your data columns to the Import_Sketches_Template.xlsx file, replacing the sample columns with your own information.

The Reason – Delete, Discipline – Delete, Receive Action – Delete, Received Via – Delete and Closing Method – Delete tabs include the keyword list values for the Reason, Discipline, Receive Action, Received Via and Closing Method fields. Change any of the existing values by simply typing a new value in the same cell.

For information on extending the list with additional values, please refer to Add Keyword Values to a Spreadsheet Template.

Edit the field values based on the information given in the Sketches and supplemental drawing fields section above. Add values to fields where required.

After you finish editing the Import_Sketches_Template.xlsx spreadsheet, import it into a Project Center project by opening the Sketches and Supplemental Drawings activity center and clicking Import Spreadsheet from the Tasks panel to open the Select Spreadsheet dialog box, as shown here. Locate the spreadsheet, then click Open.

After it is imported, the Import Log dialog box opens showing any import errors. Fix any errors that appear in the spreadsheet, then re-import it.

The import will not succeed until all errors are addressed.