Construction Change Directives activity center
Construction Change Directives Activity Center
Use this activity center to create, log, review, and track construction change directives electronically. Construction change directives are a part of contract management.
Project Center administrators can set which tasks appear here using the Remove Contract Management Item Tasks dialog box. Construction Change Directives
New Construction Change Directive > Create Construction Change Directive
Click to open the Create a Construction Change Directive dialog box to create a new construction change directive or to file an expected one.
New Construction Change Directive > Log Received Construction Change Directive
Click to open the Log a Received Construction Change Directive dialog box to log a construction change directive that you have received.
Create Report
Click to open the Create Report dialog box to select the type of construction change directive report to create. The report contains the contents of this log. You can customize which columns appear in reports simply by selecting which columns to show and hide in this activity center. Simply right-click on column headers to add or remove columns. A checkmark indicates the column will appear in the activity center and the report.
Import Spreadsheet
Click to open the Select Spreadsheet dialog box to select a Microsoft Excel spreadsheet containing construction change directive data that you can import. The imported construction change directives are placed in the appropriate construction change directive log based on the type imported.
View Pending Incoming
This task appears only when there are Pending Review Response construction change directives. Click to list only Pending Review Response construction change directives. Selected Construction Change DirectiveThe following list shows all available tasks for all construction change directive categories, in alphabetical order. The tasks that appear depend on which category you select from.
Add Similar Construction Change Directive
Click to create a new construction change directive based on the one selected. The new one contains most of the information from the original, except for unique identifiers such as the ID. The new one is also automatically related to the original. Supporting documents from the original are included. If the original contains a receive action with files and/or description of contents entries, the Select Files and Description of Contents dialog box opens first, enabling you to select the items to include in the new copy.
Close > Close
Click to open the Close Construction Change Directive dialog box to close the construction change directive without providing a response.
Close > Respond and Close
Click to open the Respond to Construction Change Directive and Close dialog box to file your response to the sender of the construction change directive and close it. If the construction change directive has files associated with it, the Select Files to Send dialog box will open first.
Close > Send and Close
Click to open the Send and Close Construction Change Directive dialog box to send the construction change directive to team members and close it. If the construction change directive has files associated with it, the Select Files to Send dialog box will open first.
Delete
Click to delete the construction change directive from Project Center. You must be a Project Center administrator and have a contract management role to delete construction change directives.
Forward for Review
Click to open the Forward Construction Change Directive for Review dialog box to forward the construction change directive to any contacts who are responsible for reviewing the construction change directive and to create a transmittal. If the construction change directive has received files or supporting documents associated with it, the Select Files to Forward for Review dialog box will open first so you can select the files to forward.
Modify
Click to open the Modify Construction Change Directive dialog box to edit the settings for the selected construction change directive, including due dates, email message reminder settings, and the description.
Receive
Click to open the Receive Construction Change Directive dialog box to log the receipt of an expected construction change directive.
Receive Pending Review Response
Click to open the Record Reviewer Response for Construction Change Directive dialog box to record a response received about a construction change directive via Info Exchange.
Record Reviewer Response
Click to open the Record Reviewer Response for Construction Change Directive dialog box to record a response received about a construction change directive that you forwarded to other contacts. When you receive a response back from a contact, record it using this task to track its progress.
Reopen
Click to open the Re-Open Construction Change Directive dialog box to re-open the closed construction change directive.
Review Related Action Items
This task is available only when you select an item that has related action items. Click to open the Related Action Items activity center to view action items related to the selected item.
Review Related Markup Sessions
This task is available only when you select an item that has related markup sessions. Click to open the Related Markup Sessions activity center to view information about and preview the related markup sessions.
Send
Click to open the Send Construction Change Directive dialog box to send the construction change directive to other project team members.
Send Email About construction change directive > To Sender
Click to open an email message in Microsoft Outlook to send to the contact who originally sent the construction change directive. The email message includes information about the construction change directive.
Send Email About construction change directive > To Recipients
Click to open an email message in Microsoft Outlook to send to the original construction change directive recipients as a reminder or with additional information. The email message includes information about the construction change directive.
Send Email About construction change directive > To All Reviewers
Click to open an email message in Microsoft Outlook to send to the contacts who are currently reviewing the construction change directive, as a reminder or with additional information. The email message includes information about the construction change directive.
Send Email About construction change directive > To All Participants
Click to open an email message in Microsoft Outlook to send to all construction change directive participants, including the sender, recipients, and reviewers as a reminder or with additional information. The email message includes information about the construction change directive.
View Form
Click to open the Construction Change Directive form to view or print the selected construction change directive’s history and details. Selected ActionSee Selected Action panel for more information. Access the actions by clicking the expand The file tasks apply to files in the Supporting Documents tab. See File Tasks panel. See Email Tasks panel for more information. See Related Item Tasks panel for more information. |
Construction Change DirectivesCategory drop-down listThe category drop-down list contains filters to display the construction change directives in particular categories. For example, if you want to view overdue construction change directives, select Overdue from the list. Only overdue construction change directives will appear in the log. You can also choose to display construction change directives for all project users or only construction change directives on which you are listed as the sender or recipient. Each category is explained below.
AllClick to display all construction change directives that have been entered for this project. Pending IncomingClick to display all construction change directives sent via Info Exchange that need to be received. When a construction change directive or construction change directive response is logged by a project team member on Info Exchange, it will show up in this category. DraftClick to display all construction change directives that are in draft form and have not been sent. Under ReviewClick to display construction change directives that have been received, but responses have not been sent to the construction change directive senders. When a non-expected construction change directive is first filed, it is placed in the Under Review category. Awaiting ActionClick to display construction change directives that have been received, but they:
Have not been forwarded for review, or
Have been forwarded for review, but a response has not been received, or
Have been forwarded for review and all responses have been received, but there has been no response sent to the construction change directive sender.
Forwarded for ReviewClick to display construction change directives that have been forwarded with a due date for another contact to review that have not been received back yet. Response OverdueClick to display construction change directives that have been forwarded but the responses back from the reviewers are overdue. OverdueClick to display construction change directives that were received with a due date but have not been closed yet. ExpectedClick to display all construction change directives filed as expected. Expected ResubmissionClick to display expected construction change directives that were created for construction change directives that require the sender to resubmit the construction change directive (the action taken on the construction change directive was Rejected or Revise and Resubmit). LateClick to display expected construction change directives that are late. All ClosedClick to display construction change directives that have had a response sent to the construction change directive sender and there is no further action required. Filter All ColumnsYou can filter by any text that appears in any of the columns in the log. For example, if you know the subject (or part of the subject) of the construction change directive that you are searching for (or the ID, status, due date, etc.), enter at least part of the text in this field. The construction change directives list updates automatically as you type. For example, if the construction change directive you are searching for has the number 30 somewhere in one of the columns, enter 30 in this field. The list will be narrowed down to only construction change directives that have the number 30 somewhere in one of the columns. Click to clear all filters.
Click to toggle between showing and hiding the column filter fields.
|
Add |
Click to open the Add Email Messages dialog box select an email message to add to the current construction change directive. |
Remove |
Click to remove the selected email message from the construction change directive. |
Supporting Documents tab
Use this tab to attach files to the selected construction change directive, and to view attached files. For example, if you receive a construction change directive and a particular drawing is related to it, you can use this tab to attach the drawing file to the construction change directive. Another example is if you receive a file with a construction change directive, mark it up, and want to send the marked up file to a reviewer. Also, files sent using the Add to > Construction Change Directive task are added to this tab.
The number in parentheses indicates the number of files that are attached to the construction change directive.
You can copy and paste and drag and drop files from Windows Explorer into this tab.
Change Version |
If you are using an EDMS, click to select a specific version of the file to link to the construction change directive. |
Set Order |
Click to open the Set Document Order dialog box to set the order of the documents. |
Add Files > Another Project File |
Click open the Add Supporting Documents dialog box to locate and attach a file to the construction change directive. |
Share with External > Yes |
Click to allow the selected files to be shared with external project team members through Info Exchange. |
Remove |
Click to remove the selected supporting file from the construction change directive. |
Preview tab
A preview of the selected file appears here.
Related Items tab
This tab lists all related Project Center items for the selected file.
Related Items tab
This tab lists all related Project Center items for the selected construction change directive.
Create Related > Action Item
Click to open the Identify an Action Item dialog box to create a new action item and link it to the current construction change directive.
Create Related > Transfer > Via Email
Click to open the Send Files to Email Recipients dialog box to send project files via email. Nothing is logged in this tab.
Create Related > Transfer > Via Info Exchange
Click to open the Transfer Files to a Newforma Info Exchange Server dialog box to transfer project files via your Newforma Info Exchange Server and link the transfer to the current construction change directive.
Create Related > Transmittal > Via Email
Click to open the Send Files and Create an Outgoing Transmittal dialog box to send project files via email, file an outgoing transmittal for a file transfer, and link the transfer to the current construction change directive.
Create Related > Transmittal > Via Info Exchange
Click to open the Transfer Files and Create an Outgoing Transmittal dialog box to transfer project files via your Newforma Info Exchange Server, create a new outgoing transmittal for the file transfer, and link the transfer to the current construction change directive.
Create Related > Contract Management > Contract Management Item
Click to open the Create Contract Management Item dialog box for the type of contract management item you selected to create a new CM item and link it to the current construction change directive.
Create Related > Web Link
Click to open the Create Web Link dialog box to enter a web link and automatically relate it to the selected Project Center item. After it is created, the Relation Type column will indicate Web Link, and users can double-click on it to open the website.
Relate to >
Click to select an existing project item and establish a relationship between it and the currently selected construction change directive. This gives you the ability to link two items that are related together. (For example, a markup session that is related to a construction change directive.) Select Another Project Item to open the Select Project Item dialog box to locate an item that is not in the list. When you create a relationship between two items, each item’s icon is added to the other item’s Related Items column and tab.
Click and select Yes to allow the selected web link to be shared with external project team members through Info Exchange.
Remove
Click to unlink and remove the selected project item from the Related Items tab.
Removing a related item from the Related Items tab does not remove it from the database.
The Relation Type column has two icons to indicate the relationship type:
The icon indicates that the relationship was created by a user and can be deleted (such as an action item related to a construction change directive).
The icon indicates that the relationship was created by Project Center and cannot be deleted (such as a transmittal or record copy related to a construction change directive).
Change Log tab
This tab displays a history of the actions taken on the construction change directive, including when it was created, modified, who was involved, and any details.
To access this activity center
Click Construction Change Directives from the Activities list or from the Project Home activity center.